06/25/21 – Great news to share. After a frustrating delay of many months, we have recently gotten the green light from the PARD Director to move forward into restoration construction! Our team is now reconvening to wrap up work that was halted at the beginning of the year and prepare for turning dirt at Norwood. […]
What's New
April, 2021
04/16/21 – April, 2021 – The Norwood project has now been shovel-ready for months, after a tremendous effort by our board and professional team in 2020 – accomplished entirely with private dollars. At present, we remain temporarily delayed, awaiting a response by PARD Legal and Management to our finalized Phasing & Funding plan. The contract […]
March, 2021
03/01/21 – March, 2021 – The project is temporarily on hold while we await a response from PARD Legal on the new amendment to our Parkland Agreement with the City. The plans are drawn, we are shovel-ready at the Norwood site, and our team and General Contractor are ready to move forward! The cost of […]
Jan/Feb, 2021
01/26/21 – Jan/Feb, 2021 – Another new year begins for Norwood! After a huge effort to achieve our goal of “shovel ready” before 2020 ended, the project is now in a holding pattern while we finalize a needed amendment to our legal agreement with PARD. Our team and General Contractor are ready to move forward […]
December, 2020
12/01/20 – December, 2020 – At long last, we reached the holy grail of “shovel ready” for the Norwood project last month. Permitting has wrapped up, construction documents are done, and it’s time to start restoration at the site! We are now in talks with PARD to fine-tune the phasing and create an initial construction […]