What's New

Week of March 16, 2015

2015/3/16 7:14:29  Week of 3/16/15 – What a great week for the project! With the foundation work behind us, not only did the carpenters get right inside and start stabilizing the wood structure of the house, but the weather cleared nicely for tree work as well. We were able to finish Part I of our […]

Continue Reading

Week of March 9, 2015

2015/3/8 19:09:28 Week of 3/09/15 – We have another huge milestone to announce: the new foundation is finished! The Norwood house was lowered off its last jack on Saturday the 7th, just in time to beat another round of showers. Kudos to the crew for pulling this one off. For new visitors, this is truly […]

Continue Reading

Friday, February 20, 2015

2015/2/21 13:37:48 Friday, February 20, 2015 – NEWSFLASH: the stem wall is done! Whoo hoo, this is another great milestone for the project. The concrete pour was completed late on a beautiful afternoon at the Norwood site. What a happy moment for those of us who were there to witness. Next up: lowering the bungalow […]

Continue Reading

Week of February 16, 2015

2015/2/17 8:22:11 Week of 2/16/15 – We’re in a bit of a lull right now while we wait for our foundation crew to return to the Norwood site and build the stem wall. That’s the reality of construction in Austin, TX – it’s called “get in line.” Patience is called for. The house is in […]

Continue Reading

Week of February 2, 2015

2015/2/2 16:30:33  Week of 2/2/15 – Drumroll again…and another NEWSFLASH: the house is back in place! Yep, impending rain motivated our movers to hustle the schedule and get our dear Norwood House back on top of the hill. Over the last week, the grade beam was backfilled with soil, the pad leveled and raked, and […]

Continue Reading

  • « Go to Previous Page
  • Page 1
  • Interim pages omitted …
  • Page 11
  • Page 12
  • Page 13
  • Page 14
  • Page 15
  • Interim pages omitted …
  • Page 21
  • Go to Next Page »

Footer

How You Can Help

Saving Norwood has been a people’s project from the beginning. Donations via NPF have ended, but there ARE ways you can help move the project forward:

How to Help

  • Facebook
  • The House
  • The Project
  • Gallery
  • FAQs
  • Contact
  • Help

© 2012–2025 . All Rights Reserved.

Privacy Policy | Terms and Conditions | Website by Logical Things